Question:
In an effort to manage scope, the MSF team has decided to deliver key
functionality first and defer less critical functionality until later. Which MSF
technique are they employing?
A. Phasing
B. Stepping
C. Releasing
D. Versioning
E. Version control
functionality first and defer less critical functionality until later. Which MSF
technique are they employing?
A. Phasing
B. Stepping
C. Releasing
D. Versioning
E. Version control
| # | 33 |
| Answer: | D |
| Answer Explanation |
A fundamental development strategy at Microsoft is to divide large projects into multiple
|