Question:
What is the goal that should be achieved during the second phase of an MSF
project?
A. Identify customer requirements.
B. Deliver a completed functional specification.
C. Achieve consensus between stakeholders and the project team.
D. Create the solution architecture and design, project plans, and schedules.
E. Calculate and document the probability, impact, and exposure for all project
risks.
# 32
Answer: D
Answer Explanation

The following deliverables are produced during the planning phase:
Functional specification Risk management plan Master project plan and master project
schedule Microsoft White Pages

Marked for review: No
Comments for review:

74-100 Microsoft Solution Framework (MSF) Practitioner