Question:
Which MSF deliverables tell the team what to build, when to build, and how to
build?
A. Solutions concept plan, the fixed-ship date, and the development plan
B. Vision/scope document, the master project schedule, and the design plan
C. Functional specifications, the master project schedule, and the master project
plan
D. Technical specifications, the master development schedule, and the
development plan
build?
A. Solutions concept plan, the fixed-ship date, and the development plan
B. Vision/scope document, the master project schedule, and the design plan
C. Functional specifications, the master project schedule, and the master project
plan
D. Technical specifications, the master development schedule, and the
development plan
| # | 28 |
| Answer: | C |
| Answer Explanation |
The functional specification serves multiple purposes, such as:
|