Question:
A team has been assembled for a small project. Because of the scope of this
project, and resource constraints, there are only five people available to fulfil the
MSF roles on the team. In this situation, what is a potential risk condition?
A. The project is too small for an MSF team.
B. Product manager and user experience roles are combined.
C. Comprehensive training materials are not complete on time.
D. Needs of the customer and the user are not adequately balanced.
# 25
Answer: B
Answer Explanation

When you have a small project team members roles have to be combined. As stated in the
Team readiness White pages the product management role and user experience role
become combined.

Marked for review: No
Comments for review:

74-100 Microsoft Solution Framework (MSF) Practitioner