Question:
An MSF team is base lining functional specifications for an upcoming major
milestone review. What is the name of this major milestone?
A. Vision/scope approved
B. Project plans approved
C. Requirements analysis complete
D. Functional specifications baselined
milestone review. What is the name of this major milestone?
A. Vision/scope approved
B. Project plans approved
C. Requirements analysis complete
D. Functional specifications baselined
| # | 23 |
| Answer: | B |
| Answer Explanation |
Base lining functional specs is part of phase two. The major milestone of phase two is
|
| Marked for review: | No |