Question:
For which activities is the program management role mainly responsible during
the second phase? (Choose two)
A. Preparing a budget.
B. Writing site preparation checklists.
C. Preparing the master project schedule.
D. Conceptual, logical and physical design.
E. Preparing each of the plans for the project.
the second phase? (Choose two)
A. Preparing a budget.
B. Writing site preparation checklists.
C. Preparing the master project schedule.
D. Conceptual, logical and physical design.
E. Preparing each of the plans for the project.
| # | 22 |
| Answer: | A C |
| Answer Explanation |
Program Management
|