Question:
You are a consultant with extensive MSF experience. You have been hired by
Abc to analyze an IT project that is over budget and in jeopardy of being
cancelled. Through interviews with existing team members you find that all team
members are focusing on development and no one is responsible for testing the
solution. Management asks you to describe how using MSF could have helped the
project to succeed. What is your response? (Choose two)
A. MSF recommends distinct roles to ensure the separation of development and
testing functions.
B. MSF combined the development and test functions so developers can test the
piece of the solution they created.
C. The MSF quality assurance role cluster is responsible for testing and can help
to ensure the solution works properly before it is released.
D. In MSF, project management is responsible for assigning tasks and
designating which team members are responsible for development and which
team members are responsible for testing.
E. MSF breaks down a project into phases with distinct milestones. The MSF
stabilizing phase would be implemented to ensure the entire solution goes
through usage testing outside of development.
Abc to analyze an IT project that is over budget and in jeopardy of being
cancelled. Through interviews with existing team members you find that all team
members are focusing on development and no one is responsible for testing the
solution. Management asks you to describe how using MSF could have helped the
project to succeed. What is your response? (Choose two)
A. MSF recommends distinct roles to ensure the separation of development and
testing functions.
B. MSF combined the development and test functions so developers can test the
piece of the solution they created.
C. The MSF quality assurance role cluster is responsible for testing and can help
to ensure the solution works properly before it is released.
D. In MSF, project management is responsible for assigning tasks and
designating which team members are responsible for development and which
team members are responsible for testing.
E. MSF breaks down a project into phases with distinct milestones. The MSF
stabilizing phase would be implemented to ensure the entire solution goes
through usage testing outside of development.
| # | 16 |
| Answer: | A E |
| Marked for review: | No |
| Comments for review: | |