Question:
When managing scope, it is always best to _____.
A. Defer new features to later releases.
B. Make sure the customer is satisfied.
C. Make sure user effectiveness is enhanced.
D. Consider the risks of changes to the scope.
E. Allow those building to solution to manage it.
A. Defer new features to later releases.
B. Make sure the customer is satisfied.
C. Make sure user effectiveness is enhanced.
D. Consider the risks of changes to the scope.
E. Allow those building to solution to manage it.
| # | 3 |
| Answer: | D |
| Answer Explanation |
Managing scope includes clarifying the scope early and good project tracking and change
|