Question:
The goal of the MSF Planning Phase is to create the ______.
A. Vision/scope, project plans, and project schedules
B. Design goals. project structure, and project schedule
C. Testing approach, project budget, and project pilot plan
D. Business case, technical specification, and project charter
E. Localization plan, vision/scope, and project master schedule
F. Design goals, project structure, and project testing approach
G. Solution architecture and design, project plans, and project schedules
A. Vision/scope, project plans, and project schedules
B. Design goals. project structure, and project schedule
C. Testing approach, project budget, and project pilot plan
D. Business case, technical specification, and project charter
E. Localization plan, vision/scope, and project master schedule
F. Design goals, project structure, and project testing approach
G. Solution architecture and design, project plans, and project schedules
| # | 2 |
| Answer: | G |
| Answer Explanation |
the planning phase is when the bulk of the planning for the project is completed. During
|