Question:
Which deliverables should be baselined during the second phase of the MSF
Process Model? (Choose two)
A. Vision/scope
B. Project charter
C. Master project plan
D. Technical specification
E. Initial risk assessment
F. Master project schedule
# 1
Answer: C F
Answer Explanation

The deliverables for the second Phase of the MSF are:
1. Functional Specifications
2. Risk Management Plan
3. Master Project Plan and Master Project Schedule Microsoft White Pages MSF Process
Model V 3.1