# Question Answer Actions
1 Which deliverables should be baselined during the second phase of the MSFProcess Model? (Choose two)A... C F
2 The goal of the MSF Planning Phase is to create the ______.A. Vision/scope, project plans, and projec... G
3 When managing scope, it is always best to _____.A. Defer new features to later releases.B. Make sure ... D
4 The team can assess the needs of those who will be directly impacted by thedeployed solution by draft... B
5 Which deliverable of the first phase of the MSF Process Model defines theapproach the team will take ... D
6 What is the goal of the first phase of the MSF Process Model?A. To determine the project costs and de... C
7 In which activities is the release management role engaged during the fourthphase of the MSF Process ... A D
8 What does the MSF Process Model do? (Choose two)A. Emphasizes planning over design.B. Maintains regul... B D
9 You have been asked with identifying and selecting the staff for developing anddeploying anew contact... D
10 Abc is migrating its financial systems from a host-based legacy system, to a webbasedsystem. Abc will... F
11 Which MSF role cluster is accountable for risk management activities?A. TestB. DevelopmentC. User exp... G
12 A team of 18 people is tasked with completing a large, complex project with threekey feature sets of ... C
13 Which statements are true? (Choose two)A. The MSF development role cluster coordinates with users.B. ... C D
14 Which are functional areas of the MSF product management role cluster?(Choose two)A. LogisticsB. Mark... B D
15 Which key concepts are a part of the MSF Team Model? (Choose two)A. Team of peersB. Willingness to le... A B
16 You are a consultant with extensive MSF experience. You have been hired byAbc to analyze an IT projec... A E
17 To increase the likelihood of project success, MSF offers guidance in how to____.A. Organize people a... A
18 Which statement is true about the design views created during the second phaseof the MSF Process Mode... C
19 Traceability is maintained by combining the concepts and practices of _______.A. Feature creep, objec... E
20 Which statement is true about creating the vision/scope document?A. Creating the vision/scope documen... A
21 What are recommended deliverables in the first phase of the MSF ProcessModel? (Choose three)A. Projec... D E G
22 For which activities is the program management role mainly responsible duringthe second phase? (Choos... A C
23 An MSF team is base lining functional specifications for an upcoming majormilestone review. What is t... B
24 Abc has an in-bound call center which handles an average of 10,000 calls per day,in response to order... B C
25 A team has been assembled for a small project. Because of the scope of thisproject, and resource cons... B
26 You are assigned a large, complex project that requires a multi-lingual graphicalinterface. What are ... B C
27 What are responsibilities associated with the MSF test role cluster? (Choosethree)A. Managing the bui... A C E
28 Which MSF deliverables tell the team what to build, when to build, and how tobuild?A. Solutions conce... C
29 You are a consultant with extensive MSF experience. You have been hired byAbc to analyze an IT projec... C
30 Which MSF characteristics make it applicable in a broad range of ITorganizations and projects? (Choos... A B E
31 You are working on the design of your solution and are currently conductinginterviews with the busine... D
32 What is the goal that should be achieved during the second phase of an MSFproject?A. Identify custome... D
33 In an effort to manage scope, the MSF team has decided to deliver keyfunctionality first and defer le... D
34 At which interim milestone of the first phase of the MSF Process Model is therepreliminary agreement ... C
35 What is a purpose of MSF's iterative approach?A. To minimize risk.B. To clarify team roles.C. To asse... A
36 A team has been assembled for a small project. Because of the scope of theproject, and resource const... D
37 Which combination of MSF role clusters owns risk management?A. Project management, developmentB. Test... F
38 Which MSF role cluster is responsible for the following functional areas?Technology consulting Implem... A
39 What is the structure of the MSF team role cluster?A. Roles->TasksB. Roles->Functional areasC. Roles-... B